Fortune Telling Collection - Ziwei fortune-telling - Planned Completion Time of Wei Zi Road Viaduct in Chuzhou

Planned Completion Time of Wei Zi Road Viaduct in Chuzhou

When is the planned completion of Wei Zi Road Viaduct in Chuzhou? The planned completion time of Wei Zi Road Viaduct in Chuzhou is 65438+February 2023. According to the key project construction plan of Chuzhou in 2022, the first phase of Wei Zi Road Viaduct (Liu Qing Road-Huayuan Road) is scheduled to start in September 2022, with a total investment of about152.5 million yuan and a construction period of about10.05 months. 15 months equals 1 year and 3 months, and September 2022 plus 1 month equals 65438+February 2023, so the planned completion time of Wei Zi Road Viaduct in Chuzhou is 65438+February 2023.